LIBRARY BRANCH CLOSURE

Erindale Library will be closed Saturday, 27 April 2024.

Return chute remains open.

All other branches will be open at normal hours.

We apologise for any inconvenience.

HMSS 0281 Thiess Construction Photographs


ACT Heritage Library Manuscript Collection

HMSS 0281 Thiess Construction Photograph Album

Scope and Content Notes

 

Call Number

HMSS 0281

Collection 

Thiess Construction Photograph Album

Date Range

1962-1970

Quantity

0.3m (1 oversized box)

Access Conditions

open

Copying conditions

Unavailable for reproduction

Related Collections

 

This album was put together by William ‘Bill’ Day, of Sydney, an engineering draughtsman who worked for Thiess on NSW and ACT projects from about 1962 until his retirement in 2004/2005. Bill worked on the drawings for both Googong and Corin Dams, and took most of the photographs in the album. After his retirement, Bill gave the album to Phil Butler.

Phil worked with Thiess from 1969 until 2011, beginning as an apprentice plant operator and ending as site manager/supervisor on projects throughout Australia. In Canberra, he worked mainly on roads and subdivisions, but also on some remedial work on Lake Burley Griffin foreshores, including the south bank of Central Basin. Phil has supplied much of the technical detail for the photographs, as well as some background stories.  Information supplied February 2012.

Thiess undertook most of the earthmoving infrastructure work for the National Capital Development Commission and later authorities, including Lake Burley Griffin, roads and subdivisions. These photographs form a valuable record of a major period in the development of Canberra.

 

BOX LIST 

PAGE

PHOTOGRAPHER

DESCRIPTION

DATE

B/W OR COL

SIZE IN CM

Loose

Capital J. Plan Printing and Photographic Co. Ltd

Excavating basement for Defence Department Offices, Canberra; Caterpillar D8 bulldozer (left), push loading Caterpillar DW21 open bowl scraper. The building at left was later demolished

04/05/1962

b/w

20 x 25

1

Capital J. Plan Printing and Photographic Co. Ltd

Forming abutments for Canberra's first flyover bridge at Adelaide Avenue and Hopetoun Circuit

1962

b/w

20 x 25

2

William Day

Part of "formal" lake shore in front of Parliament House, looking towards Russell Offices

1962

b/w

13 x 10

2

 William Day

Government House Project at road level; the stairway leads to Government House from the landing stage on Lake Burley Griffin; M Stokman was the stonework subcontractor for this project

1962

b/w

13 x 10

2

 William Day

Lindsay Greenwood starts the new Buckeye trencher in the subdivision at Curtin

1963

b/w

13 x 10

2

 William Day

Winning rock for the walls of Lake Burley Griffin, using a Caterpillar D8 with rock rake. Left to right: Ron Maggs (foreman), J R Barkla (area manager), M Stokman (stonework subcontractor)

Ca 1962

b/w

13 x 10

3

 William Day

Australian Mint basement, cut in rock - hard work excavating, according to the foreman

1962

b/w

13 x 10

3

 William Day

Weir on Murrumbidgee River

1962

b/w

13 x 10

3

Capital J. Plan Printing and Photographic Co. Ltd

Excavating basement for Defence Department Offices, Russell; Caterpillar D8 bulldozer, right, push loading Caterpillar DW21 open bowl scraper. The building at left was later demolished

04/05/1962

b/w

13 x 10

4

Snowy Mountains Authority

Constructing Lake Burley Griffin; Commonwealth Avenue Bridge top left, Aspen Island and Kings Avenue Bridge at top right, Riverside huts at centre right  (57-272 Aerial Run 3 Canberra Lake)

23/05/1963

b/w

19 x 21

5

Snowy Mountains Authority

Over Starlight Drive Inn, Watson and  Canberra Showground (57-73 Aerial)

Ca May 1963

b/w

19 x 21

6

Snowy Mountains Authority

Civic over City Hill, Vernon Circle, London Circuit (57-240 Aerial Run 1 Canberra Lake)

23/05/1963

b/w

19 x 21

7

Snowy Mountains Authority

Parkes over Hotel Canberra; Albert Hall; Commonwealth Avenue; National Rose Gardens and King George V Memorial top right;  Lake Burley Griffin under construction top left (57-270 Aerial Run 3 Canberra Lake)

23/05/1963

b/w

19 x 21

8

Snowy Mountains Authority

Constructing Lake Burley Griffin; Aspen Island bottom right; Kings Avenue, right, from the bridge to Australian American Memorial and Russell Offices; Blundell’s Cottage bottom left; Campbell top left (57-274 Aerial Run 3 Canberra Lake)

23/05/1963

b/w

19 x 21

9

 Snowy Mountains Authority

Scrivener Dam under construction top left; Yarralumla Nursery lower centre; looking north north west (57-254 Aerial Run 2 Canberra Lake)

23/05/1963

b/w

19 x 21

10

 Snowy Mountains Authority

West Basin under construction; Academy of Science centre right; Royal Canberra Hospital, Acton, top left; Commonwealth Avenue Bridge bottom left (57-244 Aerial Run 2 Canberra Lake)

23/05/1963

b/w

19 x 21

11

 Snowy Mountains Authority

Constructing Lake Burley Griffin; ANU campus at bottom, Springbank Island under construction centre left; sand dumps (parallel rows) on beaches under construction in West Basin (57-246 Aerial Run 2 Canberra Lake)

23/05/1963

b/w

19 x 21

12

 Snowy Mountains Authority

Constructing Lake Burley Griffin; Weston Park; Yarralumla Nursery top left (57-250 Aerial Run 2 Canberra Lake)

23/05/1963

b/w

19 x 21

13

 Snowy Mountains Authority

Constructing Lake Burley Griffin; Yarralumla Nursery bottom left; overlooking future Yarramundi Reach (57-252 Aerial Run 2 Canberra Lake)

23/05/1963

b/w

19 x 21

14

 Snowy Mountains Authority

Constructing Lake Burley Griffin; Weston Park right; lower slopes of Black Mountain at top, original Lady Denman Drive/future Parkes Way, Glenloch Interchange site at left (57-232 Aerial Run 1 Canberra Lake)

23/05/1963

b/w

19 x 21

15

 Snowy Mountains Authority

Constructing Lake Burley Griffin; ANU Institute of Advanced  Studies beside Sullivan’s Creek, centre (57-236 Aerial Run 1 Canberra Lake)

23/05/1963

b/w

19 x 21

16

 Snowy Mountains Authority

Constructing Lake Burley Griffin; ANU; Academy of Science upper centre; West Basin under construction right; London Circuit centre top (57-238 Aerial Run 1 Canberra Lake)

23/05/1963

b/w

19 x 21

17

 Snowy Mountains Authority

Constructing Lake Burley Griffin; Commonwealth Avenue Bridge top left; Regatta Point kiosk centre left; Mulwala House centre; Olympic Pool; Reid House lower right; Commonwealth Gardens under construction lower left (57-242 Aerial Run 2 Canberra Lake)

23/05/1963

b/w

19 x 21

18

 Snowy Mountains Authority

Looking from Banks St along Schlich St, Yarralumla; Tarcoola Reach under construction left (57-264 Aerial Run 3 Canberra Lake)

23/05/1963

b/w

19 x 21

19

 Snowy Mountains Authority

Stirling Park centre; Fitzgerald Street Yarralumla centre right (57-266 Aerial Run 3 Canberra Lake)

23/05/1963

b/w

19 x 21

20

 Snowy Mountains Authority

Hotel Canberra and Albert Hall top right; Royal Canberra Hospital centre left (57-268 Aerial Run 3 Canberra Lake)

23/05/1963

b/w

19 x 21

21

 Snowy Mountains Authority

Constructing Lake Burley Griffin; Black Mountain Peninsula top; Spinnaker Island the dark oval at centre right (57-248 Aerial Run 2 Canberra Lake)

23/05/1963

b/w

19 x 21

22

 Snowy Mountains Authority

Constructing Lake Burley Griffin; Northwest shoreline of Weston Park top right; Acacia Inlet on opposite bank of Molonglo River; cork oak plantation bottom left corner; future Glenloch Interchange will occupy the central open space  (57-230 Aerial Run 1 Canberra Lake)

23/05/1963

b/w

19 x 21

23

Snowy Mountains Authority

ANU from London Circuit; Turner lower right; West Basin lower left (57-161 Aerial)

Ca May 1963

b/w

19 x 21

24

Snowy Mountains Authority

Government House bottom; Royal Canberra Golf Course top; planting circles for trees between Lady Denman and Dunrossil Drives bottom right (57-250 Aerial Run 3 Canberra Lake)

23/05/1963

b/w

19 x 21

25

William Day

Excavation of bad or ‘soft’ spot, possibly in Belconnen, using a Caterpillar 12F grader; Gaetano Decimo (standing) was a leading hand grade checker. A soft spot is stale ground which will not support the impact loading of vehicular traffic

Early 1960s

b/w

9 x 13

25

 William Day

Excavation for road formation, using Caterpillar 612 open bowl scraper being push loaded by Caterpillar 824 rubber tyred bulldozer

Early 1960s

b/w

9 x 13

25

 William Day

Poclain hydraulic backhoe trench excavations, Belconnen

Ca 1968

Col

 9 x 9

25

 William Day

Canberra College of Advanced Education, excavating for foundations using Caterpillar 621 scraper and Caterpillar 824 bulldozer

Ca 1968

Col

 9 x 9

25

 William Day

Canberra College of Advanced Education, excavating for foundations using Caterpillar 621 scraper and Caterpillar 824 bulldozer

Ca 1968

Col

 9 x 9

26

 William Day

View from Mt Painter showing Belconnen suburb of Cook with Canberra High School in centre

Ca 1970

Col

 9 x 13

26

 William Day

View of Woden Valley

Ca 1970

Col

 9 x 13

26

 William Day

View from Mt Painter showing Lake Burley Griffin and Southern Canberra

Ca 1970

Col

 9 x 13

26

 William Day

Aerial view showing Weston Creek Neighbourhood 3

Ca 1970

Col

 9 x 13

27

 William Day

Aerial view of the Weston Creek area

Ca 1970

Col

 9 x 13

27

 William Day

Aerial view of the Weston Creek area

Ca 1970

Col

 9 x 13

27

 William Day

Aerial view of the Weston Creek area

Ca 1970

Col

 9 x 13

27

 William Day

Road construction on Weston Creek 2A; equipment left to right: Caterpillar 12F grader, Wabco 111A elevating scraper, two McDonald 3 point steel rollers

Ca 1970

Col

 9 x 13

28

 William Day

Aerial view of roadmaking in Higgins; Kingsford Smith Drive at top; pine tree plantation at Latham, corner Southern Cross and Kingsford Smith Drives

Ca 1969

Col

 9 x 13

28

 William Day

Aerial view of roadmaking in Higgins; Kingsford Smith Drive at top; pine tree plantation at Latham, corner Southern Cross and Kingsford Smith Drives

Ca 1969

Col

 9 x 13

28

 William Day

Roadwork in Belconnen, using Caterpillar 12F grader with Autocar water truck; Kingsford Smith Drive leading to top of image; Southern Cross Drive across lower part

Ca 1969

Col

 9 x 13

28

 William Day

Construction of Kingsford Smith Drive, Belconnen; equipment left to right: Caterpillar 621J elevating scraper, John Deere front end loader/backhoe, Tommy Birkland’s grader which he used for over 30 years as an owner-operated grader

Ca 1969

Col

 9 x 13

29

 William Day

Aerial view of Adelaide Avenue and Hopetoun Circuit flyover

Ca 1969

Col

 9 x 13

29

 William Day

Aerial view of Black Mountain Peninsula

Ca 1969

Col

 9 x 13

29

 William Day

Aerial view of Jamison Group Centre, Belconnen

Ca 1969

Col

 9 x 13

29

 William Day

Aerial view of Jamison Group Centre, Belconnen,

Ca 1969

Col

 9 x 13

30

 William Day

Aerial view of Belconnen showing suburb of Aranda in foreground and Jamison Group Centre in centre, with new Canberra High School at lower right

Ca 1969

Col

 9 x 13

30

 William Day

Aerial view of Woden showing Woden Town Centre (bottom left hand corner) and Phillip Industrial Area 

Ca 1969

Col

 9 x 13

30

 William Day

Aerial view of Woden Valley

Ca 1969

Col

 9 x 13

30

 William Day

Aerial view showing Phillip  Departmental Offices, Woden Town Centre and Phillip Industrial Area

Ca 1969

Col

 9 x 13

31

 William Day

Aerial view of Woden showing Woden Town Centre and Phillip Industrial Area

Ca 1969

Col

 9 x 13

31

 William Day

Aerial view of Woden

Ca 1969

Col

 9 x 13

31

 William Day

View from Black Mountain looking east over Lake Burley Griffin showing the Hospital Peninsula

Ca 1970

Col

 9 x 13

31

 William Day

Aerial view of Lake Burley Griffin showing Commonwealth Avenue Bridge and the Hospital on Acton Peninsula, city buildings bottom right hand corner

Ca 1970

Col

 9 x 13

32

 William Day

Aerial view showing Anzac Parade and the Australian National War Memorial with Parliamentary Triangle in background

Ca 1970

Col

 9 x 13

32

 William Day

Aerial view of Anzac Parade and Australian National War Memorial

Ca 1970

Col

 9 x 13

32

 William Day

View taken from Australian National War Memorial looking down Anzac parade onto Parliament House

Ca 1970

Col

 9 x 13

32

 William Day

Aerial view of Woden showing subdivision works, looking south from Yarra Glen over Woden Town Centre

Ca 1969

Col

 9 x 13

33

 William Day

Aerial view from Campbell across Anzac Parade to Reid and Civic

 July 1972

Col

 9 x 13

33

 William Day

Aerial view of southern end of Anzac Parade, showing Rond Pond and Terraces, Anzac Park Offices looking west to Civic 

 July 1972

Col

 9 x 13

33

 William Day

Bantam 20 ton hydraulic mobile crane, in use on Lake Ginninderra trunk sewer line

 July 1972

Col

 9 x 13

33

 William Day

Three Caterpillar 621 open bowl scrapers, at end of a road cutting, possibly Ginninderra Drive at Kaleen; Caterpillar DH8 bulldozer in left background; Komatsu 155 bulldozer behind second row of scrapers (this was first used on Ginninderra Drive) 

 July 1972

Col

 9 x 13

34-58

Not used

 

 

 

 

59

 William Day

Aerial view of Googong Dam immediately after diversion of the river; diversion tunnel entrance in centre; exit beyond; old homestead bottom left; workshop and offices for Thiess Bros and NCDC centre left

June 1976

Col

21 x 26

60

 William Day

Googong Dam flood during construction; three photographs making a panorama of the floodwaters downstream from the dam wall

 15/10/1976

Col

9 x 13

60

 William Day

Googong Dam flood during construction; showing tunnel outlet

 15/10/1976

Col

9 x 13

60

 William Day

Googong Dam flood during construction; showing tunnel inlet

 15/10/1976

Col

9 x 13

60

 William Day

Googong Dam flood during construction; showing dam wall

 15/10/1976

Col

9 x 13

60

 William Day

Googong Dam flood during construction; showing dam wall

 15/10/1976

Col

9 x 13

61

 William Day

Googong Dam flood during construction; upstream

 15/10/1976

Col

9 x 13

61

 William Day

Googong Dam flood during construction; upstream

 15/10/1976

Col

9 x 13

61

 William Day

Googong Dam flood during construction; upstream

 15/10/1976

Col

9 x 13

61

 William Day

Googong Dam flood during construction; upstream

 15/10/1976

Col

9 x 13

61

 William Day

Googong Dam flood during construction; upstream

 15/10/1976

Col

9 x 13

61

 William Day

Googong Dam flood during construction; inlet tunnel

 15/10/1976

Col

9 x 13

62

 William Day

Googong Dam flood during construction; bottom of spillway

 15/10/1976

Col

9 x 13

62

 William Day

Googong Dam flood during construction; bottom of spillway (left of previous photograph)

 15/10/1976

Col

9 x 13

62

 William Day

Googong Dam flood during construction; downstream

 15/10/1976

Col

9 x 13

62

 William Day

Googong Dam flood during construction; downstream; middle man is Ray Green, American engineer on project

 15/10/1976

Col

9 x 13

62

 William Day

Googong Dam flood during construction; Komatsu 155 bulldozer, operator Charlie Carr

 15/10/1976

Col

9 x 13

62

 William Day

Googong Dam flood during construction

 15/10/1976

Col

9 x 13

63

 William Day

Googong Dam flood during construction; washouts on access road

 15/10/1976

Col

9 x 13

63

 William Day

Googong Dam flood during construction; washouts on access road

 15/10/1976

Col

9 x 13

63

 William Day

Googong Dam flood during construction; washouts on access road

 15/10/1976

Col

9 x 13

63

 William Day

Googong Dam flood during construction; washouts on access road

 15/10/1976

Col

9 x 13

63

 William Day

Googong Dam flood during construction; washouts on access road

 15/10/1976

Col

9 x 13

63

 William Day

Googong Dam flood during construction; washouts on access road

 15/10/1976

Col

9 x 13

64a

 William Day

Googong Dam flood during construction; concrete column cracked by force of water

 15/10/1976

Col

9 x 13

64b

 William Day

Googong Dam flood during construction; face of dam wall, mesh with rockfill behind

 15/10/1976

Col

9 x 13

64c

 William Day

Googong Dam flood during construction; face of dam wall, mesh with rockfill behind

 15/10/1976

Col

9 x 13

64d

 William Day

Googong Dam flood during construction; face of dam wall, mesh with rockfill behind

 15/10/1976

Col

9 x 13

64e

 William Day

Googong Dam flood during construction; 35 ton Euclid dump truck; Caterpillar D8H bulldozer assisting with remediation work on dam wall

 15/10/1976

Col

9 x 13

64f

 William Day

Googong Dam flood during construction; Kato 1100 excavator providing rock for fill

 15/10/1976

Col

9 x 13

64g

 William Day

Googong Dam flood during construction; men in yellow rain gear; Thiess employed any local idle labour to remediate and repair the dam wall, because of fears of a second flood within 2 days of the first; Kato 1100 excavator providing rock for fill; green Euclid front end loader

 15/10/1976

Col

9 x 13

65

 William Day

Googong Dam flood during construction; dam wall, downstream face

 15/10/1976

Col

9 x 13

65

 William Day

Googong Dam flood during construction; dam wall, downstream face

 15/10/1976

Col

9 x 13

65

 William Day

Googong Dam flood during construction; dam wall, downstream face

 15/10/1976

Col

9 x 13

65

 William Day

Googong Dam flood during construction; upstream

 15/10/1976

Col

9 x 13

65

 William Day

Googong Dam flood during construction; Lima dragline; washed out in flood, written off by insurance; rebuilt and reused by Thiess

 15/10/1976

Col

9 x 13

66

 William Day

Googong Dam flood during construction; upstream; rock crushing and screening plant, centre, for supply to onsite concrete works; dam wall at top right, workshops and offices on crest of hill, centre

 15/10/1976

Col

9 x 13

66

 William Day

Googong Dam flood during construction; upstream

 15/10/1976

Col

9 x 13

66

 William Day

Googong Dam flood during construction; upstream

 15/10/1976

Col

9 x 13

66

 William Day

 Unknown dam

nd

Col

9 x 13

67

 William Day

 Outlet pipes at Googong Dam leading to treatment plant before distribution to Canberra and Queanbeyan

April 1977

Col

9 x 13

67

 William Day

Outlet pipes at Googong Dam leading to treatment plant before distribution to Canberra and Queanbeyan

April 1977

Col

9 x 13

67

 William Day

Outlet pipes at Googong Dam leading to treatment plant before distribution to Canberra and Queanbeyan

April 1977

Col

9 x 13

68

 William Day

Intake structure and dam wall, Googong Dam, upstream

23/03/1977

Col

21 x 26

69-   100

Not used

 

 

 

 

101

 William Day

Corin Dam, site prior to diversion of Cotter River; workshop and offices and miscellaneous plant, top left

12/11/1966

b/w

17 x 22

102

 William Day

Corin Dam, Caterpillar D8H bulldozers releasing initial coffer dam

12/11/1966

b/w

17 x 22

103

 William Day

Corin Dam, 35 ton Euclid trucks and Caterpillar D8H bulldozer sealing off main cofferdam prior to diverting water through the tunnel

12/11/1966

b/w

17 x 22

104

 William Day

Corin Dam, 35 ton Euclid trucks and CatD8H bulldozer sealing off main cofferdam prior to diverting water through the tunnel, second stage

12/11/1966

b/w

17 x 22

105

 William Day

Corin Dam, sealing off main cofferdam prior to diverting water through the tunnel, third stage cofferdam and diversion of water nearly complete

12/11/1966

b/w

17 x 22

106

 William Day

Corin Dam, Cotter River diversion – full volume of water flowing through tunnel

12/11/1966

b/w

17 x 22

107

 William Day

Corin Dam, Cotter River diversion – full volume of water flowing through tunnel

12/11/1966

b/w

17 x 22

108

 William Day

Corin Dam, special compaction of zone 1 material in cut-off trench, using an air-operated pogo stick

 25/02/1967

b/w

9 x 12

108

 William Day

Corin Dam, drilling operations in quarry, using an air track drill

 18/10/1966

b/w

9 x 12

108

 William Day

Corin Dam, view of the camp site taken from housing site

 12/01/1967

b/w

9 x 12

109

 William Day

Corin Dam, Caterpillar 988 front end loader loading 35 ton Euclid in quarry

 18/10/1966

b/w

9 x 12

109

 William Day

Corin Dam, P&H lattice boom crane pouring concrete on walls adjacent to crest structure in spillway 

 13/03/1967

b/w

9 x 12

109

 William Day

Corin Dam, general view of workshop area in foreground and borrow areas and filter processing plant in background

 26/05/1967

b/w

9 x 12

109

 William Day

Corin Dam, view taken from the downstream tail of the spillway looking upstream; the air operated drill is built on an ex-Army World War 2 tank base

26/05/1967

b/w

9 x 12

110

 William Day

General view of Corin Dam with spillway in background; composite of several photographs to form a panorama

26/05/1967

b/w

19 x 40

110

 William Day

Downstream face of Corin Dam; dam topped out

Ca 1967

Col

9 x 9

110

 William Day

Corin Dam, looking down spillway from bridge

Ca 1967

Col

9 x 9

111

 William Day

Corin Dam, looking up spillway from bridge, showing unfinished prestressed spillway entrance crest at left

Ca 1967

Col

9 x 9

111

 William Day

Corin Dam, looking downstream at spillway bridge from inlet crest

Ca 1969

Col

9 x 9

111

 William Day

Corin Dam, looking upstream from right abutment at core material borrow area; road to quarry at middle left; note area cleared for dam

Ca 1969

Col

9 x 9

111

 William Day

Corin Dam, looking across from spillway inlet to upstream rock face of dam at left and intake structure and bridge over tunnel in centre

Ca 1969

Col

9 x 9

111

 William Day

Corin Dam, looking from office at upstream rock face of dam

Ca 1969

Col

9 x 9

111

 William Day

Corin Dam, quartzite quarry

Ca 1969

Col

9 x 9

112

 William Day

Corin Dam, Lima dragline stockpiling creek gravel for filter production; this dragline is the one later inundated in the Googong Dam flood

Ca 1967

Col

9 x 9

112

 William Day

Corin Dam, excellent view of centre core no. 1 material red, showing filters on either side and rock facings looking from left hand abutment of wall half way up

Ca 1967

Col

9 x 9

112

 William Day

Corin Dam, looking at downstream rock face from left hand abutment downstream

Ca 1967

Col

9 x 9

112

 William Day

Corin Dam, excellent view of core, filters and rock placement from left hand abutment; concrete spillway in progress in background

Ca 1967

Col

9 x 9

112

 William Day

Corin Dam, downstream rock face and part of core showing

Ca 1967

Col

9 x 9

112

 William Day

Corin Dam, looking down concrete spillway chute in progress

Ca 1967

Col

9 x 9

113

 William Day

Corin Dam, looking across at right hand abutment (cleaned off) and showing core material (decomposed granite)

Ca 1967

Col

9 x 9

113

 William Day

Corin Dam, looking from office at upstream rock face of dam; workshop centre right

Ca 1967

Col

9 x 9

113

 William Day

Corin Dam, quarry development (quartzite)

Ca 1967

Col

9 x 9

113

 William Day

Corin Dam, air-operated drills in quarry; the drills are mounted on ex-Army World War 2 tank bases

Ca 1967

Col

9 x 9

113

 William Day

Corin Dam, looking upstream at core borrow area and left hand road to quarry; dam area already cleared

Ca 1967

Col

9 x 9

113

 William Day

Corin Dam, Caterpillar 988 loading 35 ton Euclid trucks

Ca 1967

Col

9 x 9

114

 William Day

Aerial view of Corin Dam

 Ca 1970

Col

9 x 13

114

 William Day

Aerial view of Corin Dam

 Ca 1970

Col

9 x 13

114

 William Day

Aerial view of Corin Dam

 Ca 1970

Col

9 x 13

114

 William Day

Aerial view of Corin Dam

 5/03/1968

b/w

9 x 9

115

 William Day

Corin Dam, view of downstream face of dam

May 1968

Col

9 x 13

115

 William Day

Corin Dam, taken from downstream end of spillway

May 1968

Col

9 x 13

115

 William Day

Corin Dam, view taken from spillway bridge showing road pavement and guard rail fence along top of dam

May 1968

Col

9 x 11

116

 William Day

Corin Dam, view from spillway bridge showing spillway chute

May 1968

Col

9 x 13

116

 William Day

Corin Dam, view from spillway bridge showing spillway crest

May 1968

Col

9 x 13

116

 William Day

Aerial view of Corin Dam 

20/10/1969 

Col

12 x 17

loose

 William Day

View of Flood Gap, which is the end of the Outfall Channel, unknown location

26/02/1966

Col

7 x 10